Meeting 2009-03-24
Administrative and budget meeting
Mechancial
- Motors and gearboxes will be here on Friday -- will put all motors & gearboxes in the frame this weekend
- Working on building the hubs -- started this weekend (probably one or two done, push for the rest next week)
- New robot will be rolling once the hubs are assembled
- Working on adding another level to the electronics box
Electrical
- Killswitch, motor controller and power distribution boards have been sent to Gary for manufacture -- should be done by Friday
- Fuses and motor controllers have been mounted in the box
- Will be wired soon
- Intend to have everything wired by the weekend
- Need to order female headers
Software
- Andy has made progress on image processing
- Issues with GTK+ event loop delay causing motor controller issues solved by moving data processing loop to separate thread
- Began setting up Elphel 353 for streaming video to OpenCV via v4l device