Administrative and budget meeting

Mechancial

  • Motors and gearboxes will be here on Friday -- will put all motors & gearboxes in the frame this weekend
  • Working on building the hubs -- started this weekend (probably one or two done, push for the rest next week)
  • New robot will be rolling once the hubs are assembled
  • Working on adding another level to the electronics box

Electrical

  • Killswitch, motor controller and power distribution boards have been sent to Gary for manufacture -- should be done by Friday
  • Fuses and motor controllers have been mounted in the box
    • Will be wired soon
    • Intend to have everything wired by the weekend
  • Need to order female headers

Software

  • Andy has made progress on image processing
  • Issues with GTK+ event loop delay causing motor controller issues solved by moving data processing loop to separate thread
  • Began setting up Elphel 353 for streaming video to OpenCV via v4l device