Meeting 2009-04-21

Administrative meeting following spring break

Hardware

  • Working on keyways in pancakes for wheels
  • Have 5 hubs made
  • Will soon have 4 wheels, and 6 wheels soon after
  • Fixed some issues with the CAD design
  • Intend to have encoder mount done by the weekend

Electronics

  • Doing quite well; many things have been mounted
  • Making cables
  • Killswitch works
  • Today: power on the computer and test the motor controllers
  • Will get more blue 883s soon
  • Need a circuit breaker for the computer/electronics battery

Software

  • Some vision work accomplished

Misc

  • Discussed recruitment
  • Discussed simulation