Meeting 2009-12-13
Last all-team meeting before winter break
Hardware
- Have the battery plate ready to go
- Encoders ready to be mounted
- Plates on the cases ready to be mounted
- Everything done necessary for movement done by the end of this meeting
- Once have vibration data on mast will design steadycam, order paneling
Electronics
- Working on getting stuff wired
- Need to order boards -- have gerber files made
Software
- Made progress on camera calibration
- Working on CAN interface and Kalman filter
Administrative
- Looking at getting t-shirts ordered, passed around sign-up sheet
- Either gray or black, with the team logo large on the front
- Have gotten a few sponsorships
- Advanced Circuits is giving us board manufacture
- we have been given discretionary money to supplement our SGA funds
- National Instruments are giving us some equipment, though we likely won't make use of it this year